Does Increasing the Number of Projects Impact Level of Work?

From the Ask Tom mailbag –

Question:
You seem to base level of work on time span. But can’t the level of work also be defined by the number of simultaneous projects? It seems odd that doing (1) six month project is the same level of work as doing (3) six-month projects, at the same time. The time span is still six months, but juggling three projects seems more complex than executing one project?

Response:
Yes, the number of simultaneous projects does impact the level of work, but not in the way you might think. In your example of the project manager, who effectively executes (1) six month project, what is the level of work? The time span of the project would indicate that this would be S-II level of work.

And so, her manager assigns (2) simultaneous six-month projects. What is the level of work? Though the project manager may spend more hours during those six months, the level of work is still S-II.

And so, her manager assigns (3) simultaneous six-month projects. What is the level of work? Though the project manager may spend even more hours during those six months, the level of work is still S-II.

At some point, however, the project manager simply runs out of hours. The level of work doesn’t change, but the project manager passes out from exhaustion.

And so, her manager assigns (4) simultaneous six-month projects. In fact, to make the point clearer, her manager assigns (50) simultaneous six-month projects.

If the project manager is out of hours, (50) simultaneous projects cannot be done at the same level of work. To effectively execute (50) simultaneous projects, the project manager will have to delegate the direct work and create specific systems for monitoring progress and gauging quality control. The work creating the systems to monitor progress and check for quality is solid S-III.

And while the projects themselves may be completed in six months, the planning, recruiting, system design, and system testing will easily add months prior to project mobilization. Add the audit work to ensure project accuracy, phase completion and quality standards at the end of the project, and you are well over twelve months time span for these (50) projects.

So, you are correct that increasing the number of simultaneous projects impacts the level of work, but only when you run out of hours.

One thought on “Does Increasing the Number of Projects Impact Level of Work?

  1. Jason

    I like the simplicity of this article and how it is clear for readers to understand that sometimes you will need to turn away an assignment. Not only will the person be overwhelmed and produce less than desirable work for all tasks. It is very likely that a more desirable task may come along and you will not be able to take that project on at all.

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.